Wedi transforms the work of tiling

Installing Fundo in wooden floor step 2

   Position the drain body to correspond with its relevant position in the Fundo shower base unit (right). Connect the drain outlet to a 2" British Standard Pipe (solvent weld).

   Now construct a boxing around the Fundo drain to support the edges of the cut area of the flooring and to surround the drain unit. Prime and seal the wooden surfaces.
Hole prepared in firm floor

Support board and noggins 80mm below top of joist


    Infill below and around the drain body with a semi-dry sand/cement mix. Compact it around and under the drain to provide support (see left).

   Replace the floor section with an aperture cut for the top flange of the drain,  then build up the mix to level with the top of the floor (see below).